Crashing is
A. Abandoning the project
B. Completing the project with all possible haste
C. Reduction of duration for a few of the activities
D. Reduction the cost of the project with all needful modification
Answer: Reduction of duration for a few of the activities
Crashing is a schedule compression technique used to reduce or shorten the project schedule. The PM can various measures to accomplish this goal. Some of the common methods used are. Adding additional resources to the critical path tasks.
A. Abandoning the project
B. Completing the project with all possible haste
C. Reduction of duration for a few of the activities
D. Reduction the cost of the project with all needful modification
Answer: Reduction of duration for a few of the activities
Crashing is a schedule compression technique used to reduce or shorten the project schedule. The PM can various measures to accomplish this goal. Some of the common methods used are. Adding additional resources to the critical path tasks.
Project crashing is a method for shortening the project duration by reducing the time of one (or more) of the critical project activities to less than its normal activity time. This reduction in the normal activity time is referred to as crashing.